News & Events


Commissioning of utility units of phases 22-24, South Pars Gas Field Development

Commissioning of utility units of phases 22-24, South Pars Gas Field Development

(April 2019)

 

Nardis Company completed the construction, commissioning and delivery of following units:

 

  • Unit 120 electrical substations No.1 to 11
  • Unit 121 steam generation boilers A&B and C
  • Unit 123 instrument & service air system -compressors A&B
  • Unit 124 nitrogen generation plant
  • Unit 126 desalting
  • Unit 127 water polishing
  • Unit 129 waste effluent disposal
  • Unit 132 cooling water system- units 100 & 200

 

South Gas Pars Development Phases 22-24 officially handed over to the Client and inaugurated in the presence of President Dr. Rouhani, Bijan Zanganeh, the oil minister and some officials on 2019/03/17.